| Holiday
Start-up at Chemical Facility
December,
1998
'Twas
the night after Christmas and all through the facility,
not an operator of stirring or mixing ability. The
PLCs were hung in the enclosure with care, in hopes
that Superior Controls soon would be there.
On
December 26 at 6:00 P.M., the night after Christmas,
12 Superior Controls engineers and technicians began
working through the night replacing an obsolete chemical
control system. The project, itself, was fairly typical.
Superior Controls was responsible for providing and programming
two programmable logic controller (PLC) based systems
with approximately 600 input and output signals. All
field wiring including the detaching of the old system
and rewiring of the new system was implemented by Superior
Controls. Not so unusual . . . except all the field wiring
and start-up tasks had to take place within 48 hours.
This
Fortune 500, New England-based, chemical company had
a problem. Their solvent recovery and industrial waste
water treatment system was being controlled by a 12-year-old
PLC system. Obsolescence and trouble obtaining spare
parts made it essential that the PLC system be replaced.
However, four major manufacturing buildings were dependent
upon this treatment system 24-hours a day, so the only
time this continuous process could be interrupted was
during a 48-hour window during Christmas break. In addition,
the PLC system for a nearby Regenerative Thermal Oxidizer
(RETOX) had to be replaced during this same weekend.
Patty
Ascanio, lead project engineer, noted, "It was absolutely
critical that both systems be back up and running in
the allocated time. If the system is not, the entire
site would be shut down."
Although
large and complex, the industrial waste water and RETOX
systems were only two of the 11 networking PLC systems
Superior Controls had implemented at this facility during
recent years. With 11 Modicon PLCs and six FIX-based
SCADA Nodes, the entire system controls and monitors
more than 3,000 field points.
Before
the big weekend, Superior Controls and Beckwood Services,
constructed several panel inserts containing the PLCs,
I/O modules, and terminal blocks. These would fit neatly
into the old control panels after the old control equipment
was removed. The control programs were tested prior to
going on-site. The RETOX system, because of its critical
nature, was tested and simulated several times. Numerous
coordination meetings were held and contingency lists
prepared.
Mark
LaRoche, director of engineering noted that "Months of
planning resulted in complete success. Groups of engineers
and technicians worked around the clock in 12-hour shifts
through the weekend. With great efforts both systems
were rewired and back up and running in the allotted
time." Applause to all associated with the project.
|